The relocation of Lidl Romania’s headquarters,
coordinated for business continuity.
320 employees. 6 floors. 2,400 m². A clear relocation schedule: on Monday morning, the team resumed work at the new headquarters in Aviației, exactly as planned.
320
Employees relocated
5
Days of execution
2,400
m² relocated
0
Incidents reported
A new stage of growth and a headquarters
suited to an expanding organisation
Lidl Romania operates a national network of stores and a complex logistics chain. The head office in Pipera had served the company for many years. As the team grew, so did the need for a headquarters matching the company’s new operational scale.
The new head office in Aviației: 2,400 m² across 6 floors, open-plan offices, conference rooms, an internal data centre and an extensive physical archive, with documents accumulated over many years.
The project had a handover and go-live date set in advance, and every stage was planned to meet it.
- Client
- Lidl Romania
- Project type
- Corporate relocation · B2B
- Route
- Pipera → Aviației
- Year
- 2018
Operational milestones
-
A clearly defined operational schedule
On Monday at 09:00, the team was due to start work at the new headquarters. The entire moving plan was built around this deadline, with every stage prepared and coordinated in advance.
-
IT relocation planned in detail
Workstations and servers were inventoried, labelled and organised individually, for a controlled move and correct repositioning at destination.
-
Coordinated access across 6 floors
The relocation was organised within the time slots permitted by the building, including evenings and the weekend, with planned use of the goods lift and the access routes.
-
An extensive archive, managed with full traceability
The document boxes were classified, inventoried and transported under a clear chain-of-custody procedure, for an organised handover at the new headquarters.
Planning well in advance, with a Gantt plan.
Our own team. Clear coordination from start to handover.
A dedicated project manager
A single point of contact for Lidl throughout the project, responsible for coordinating the stages, the teams and the relocation schedule. The Gantt plan was tracked and updated throughout execution.
Traceability for IT equipment
Every workstation was identified and labelled individually, with details of the department, the user and its position at destination. Sensitive equipment was protected with antistatic materials and documented before transport.
Protection and insurance cover
The project was carried out under MovingBox’s Generali liability policy, within the limit and terms of the active policy. Goods and operations were managed in line with the procedures established for the project.
An in-house MovingBox team
The project was carried out by an in-house MovingBox team, organised in shifts and coordinated across the stages set out in the plan. Every team member worked according to the operational procedures and the responsibilities defined before the relocation began.
From survey to a fully operational new headquarters:
3 months of preparation, 5 days of execution
Months 1–2
Survey and planning
- ✓ Survey of the premises and inventory of furniture, IT equipment and archives
- ✓ A detailed Gantt plan, agreed together with each department
- ✓ Definition of the stages, responsibilities and access windows
- ✓ Operational briefing for the MovingBox team before the relocation began
Month 3
Packing, inventory and labelling
- ✓ Phased preparation of each department according to the agreed schedule
- ✓ A labelling and traceability system for boxes and workstations
- ✓ Over 2,000 archive boxes inventoried and managed under the chain-of-custody procedure
- ✓ Protection and packing adapted to furniture, IT equipment and sensitive goods
Days 1–2
Relocation of furniture and archives
- ✓ Coordination of operations across all 6 floors, according to the execution plan
- ✓ Handling and transport of furniture, archives and bulky pieces with the right equipment
- ✓ Unloading and positioning at destination according to the approved layout plan
- ✓ Verification of each stage before continuing the relocation
Days 3–5 · Final
Relocation of IT equipment and handover of the premises
- ✓ Servers protected, labelled and transported according to the agreed plan
- ✓ Workstations identified and positioned at destination through the labelling system
- ✓ Coordination with the IT team on the order of collection and handover of equipment
- ✓ Final check of the positioning and handover of the project according to the agreed schedule
- ★ Project completed 6 hours ahead of schedule
On Monday morning,
the new headquarters was ready for work to resume.
0
Incidents reported at handover
The equipment and goods included in the project were handed over according to plan, with no incidents reported at the time of acceptance.
–6 h
Ahead of schedule
The relocation was completed 6 hours ahead of the deadline set in the project schedule.
100%
Operational continuity
Phased execution and coordination with the Lidl teams allowed work to resume at the new headquarters exactly as planned.
“MovingBox showed us that a relocation of this scale can be managed in an organised way, with careful planning, clear communication and a team that takes ownership of every stage of the project.”
Facilities Manager, Lidl Romania